Civil Engineering & Design

Graham Lake Dam Rehabilitation

Graham Lake Dam

The Graham Lake Dam is part of the Ellsworth Project, which is owned and operated by Bangor Hydro-Electric Company (BHE). The embankment was constructed in 1923 as a semi-hydraulic fill. Engineering assessments determined that the earth embankment contained soils that were susceptible to seismically induced liquefaction. In addition, the embankment is founded on a sensitive, soft silty clay which, in conjunction with a high phreatic surface and loose soils, contributed to a low slope stability factor of safety.

A feasibility study was conducted to determine a cost-effective approach to remediation. Devine Tarbell & Associates, Inc.’s (DTA) staff designed the selected remediation and provided Owner’s Representative services on-site during construction.

DTA’s staff concluded that the most cost-effective approach to remediation was a concrete gravity flood control structure located at the downstream toe of the existing dam, integrated with the existing spillway structure. Design of the new flood control structure was constrained by the limited land available at the downstream slope, and appeared to require an extensive tieback wall to maintain the stability of the downstream slope of the dam while digging a 30-foot-deep excavation to bedrock foundation subgrade, significantly increasing project costs. As an alternative to the tieback wall, DTA’s staff developed a unique and cost effective approach using a counterweight berm, constructed in sequential cells, to replace the soft foundation soils at and below the toe of the dam, effectively buttressing stability during excavation.

The existing dam consisted of granular soils and would serve as the upstream cofferdam for the excavation during construction. To control seepage, DTA’s staff specified a deep well system. After installation of each deep well in the dam, a pumping test was conducted. The indicated hydraulic response of the dam to pumping, measured by piezometers, was evaluated using a three-dimensional groundwater flow model to assess the need for additional wells prior to excavation. Field instrumentation to monitor slope stability during excavation and construction included piezometers and slope inclinometers.

 

[back to top]

[close window]